Production Schedule





Date
Task
Description
26/10/16
Planning
Completed
1/11/16
Storyboard
Completed
3/11/16
Animatic
Completed
7/11/16
Shot list
Completed
11/11/16
Filming schedule
We will organise a date and time which will suit everyone to film our opening sequence.
16/11/16
Filming
we will film the scene of Adam walking from asda to end of the row of houses.
21/11/16
Filming
We will film Adam walking from the end of the row of houses to school.
22/11/16
Editing
Tom will edit the opening sequence to start with by adding the names of the people who produced and will star in the film.
23/11/16
Editing
Tom will add our chosen music on top of our sequence and he will ensure that it fits to all the different parts. Tom will also add the title of our film to the end of our scene.